1) Slab-on-Grade Fundamentals
Subgrade & Drainage
Strip organics, proof-roll, and compact per geotech/engineer. Provide positive drainage away from the slab (target ~5% fall for the first 10′ where feasible). Keep splash-back off panel bases.
- Well-graded base (e.g., 4–6″ compacted) as specified.
- Plan swales and downspouts before you pour.
Vapor Barrier & Reinforcement
Install a continuous vapor barrier with lapped/taped seams and puncture protection. Place reinforcement (rebar/WWF) at designed cover; typical slabs are 4–6″ — verify with engineering and code.
Tip: Coordinate slab thickness with door thresholds and base trim fastener zones.
Joints & Saw-Cuts
Cut control joints per layout and timing; align at re-entrant corners and openings. Use isolation/expansion joints at grade beams, footings, columns, and dissimilar materials.
Elevation & Access
Set finish floor elevation high enough for site drainage and snow/ice. Confirm drive widths, turning radii, and crane/lift staging if the structure requires it.
Loads drive concrete: Verify your loads & code (IBC year, wind, snow, seismic, frost) via CodeSmart™ before finalizing foundation design.
2) Rigid Frame (Red Iron) Foundations
Typical System
Isolated spread footings at main frames, tied by grade beams or slab per design. Sizes/depths resist soil bearing, overturning, and uplift; top elevations coordinate with anchors and grout space.
Component | Notes |
Main Frame Footings | Set to elevation for base-plate grout; verify bearing and rebar per plan. |
Anchor Rods | Steel templates, correct projection/embed; protect threads and check X-Y. |
Grade Beams | Tie footings laterally or support edges when specified. |
Slab | Sequence with erection as designed; confirm F-numbers where required. |
Anchors & Tolerances
Follow the manufacturer’s anchor-bolt plan exactly. Use rigid templates; verify location, projection, and plumb prior to pour. Maintain grout space and keep rods clean through finishing.
- Photo-log inspections and measurements.
- Double-nut leveling if specified.
- Never torch/slot base plates without written direction.
Sequencing
Common flow: footings → cure/strip → verify anchors → erect frames → slab. Some designs pour slab first; always follow stamped drawings and erector plan.
Inspections & Docs
Expect inspections for forms/steel, anchors, and possibly special inspections for bolting/welding. Keep stamped drawings, RFIs, and change orders on site.
Don’t freehand anchors: Field-moving anchors without engineer approval risks fit-up issues and voided warranties.
Typical System
Continuous perimeter grade beam with thickened edges or piers as needed. Columns land along the beam; the interior slab serves as the floor.
Component | Notes |
Perimeter Grade Beam | Reinforced and below frost where required; width/depth per engineering. |
Anchors/Straps | At column lines per pattern; maintain straightness and projection for base trim. |
Slab-on-Grade | 4–6″ typical; continuous vapor barrier; isolation joint to grade beam if specified. |
Frost, Elevation & Trim
Extend grade beam below frost per local criteria. Keep top of beam above exterior grade to protect panel bases. Coordinate base-trim fasteners and wall-panel laps with anchor layout.
Sequencing
Typical: excavate/grade → form & pour grade beam → set/verify anchors → backfill → prep/pour slab. Record dimensions and take photos for close-out.
Drainage Integration
Plan gutters/downspouts and surface drainage to keep the perimeter dry. Tie site swales to discharge points away from slab edges.
4) Checklists You Can Use
Before You Pour
- Soil report or bearing confirmation available.
- Local criteria verified (IBC year, wind, snow, seismic, frost) via CodeSmart™.
- Stamped foundation drawings match building drawings.
- Anchor-bolt plan reviewed with concrete sub + erector.
- Joint layout set; finish elevations confirmed.
During Placement
- Inspector sign-offs recorded (forms, steel, anchors).
- Anchors braced, templates tight, threads protected.
- Vapor barrier intact; seams taped; penetrations sealed.
- Saw-cut timing per spec; edges clean and straight.
After Cure
- Verify anchor projection/locations; record as-builts.
- Repair spalls before steel arrives; maintain grout space.
- Confirm slab flatness (F-numbers) where doors/equipment require.
Common Mistakes
- Pouring before receiving the final anchor-bolt plan.
- Punctured or muddy vapor barrier under the slab.
- No isolation joints at grade beams/footings.
- Slab elevation too low → splash-back at panel base.
Align finishes and penetrations: see Sheeting & Trim Standards and moisture strategy in Insulation 101.
5) Important
Educational guidance only. Foundations must be designed and stamped by a licensed engineer for your site conditions and loads. Always confirm requirements with your local building department.